Question: 1
A project requires five tasks to complete.
* Task A begins on day 1 and will take two days to complete.
* Task B will take six days to complete and cannot begin until task A is finished.
* Task C will take four days to complete, cannot begin before task A is finished, and must be completed before task D begins.
* Task D will take eight days to complete and cannot begin until task B is finished.
* Task E will take one day to complete and cannot begin until task D is finished.
What is the duration of the critical path?
Question: 2
A project management team is developing a project management information system (PMIS) as a
collaboration tool for internal and external stakeholders. A dashboard is updated monthly with information on the project's performance.
What type of communication method does this describe?
Question: 3
A project has five main sponsors, three of whom often challenge the project manager on the project's status. What should the project manager do to ensure continuous support from all sponsors?
Question: 4
A project's cost performance index (CPI) is 1.05 and its schedule performance index (SPI) is 0.95. Based on
this information, what is the result of the project?
Question: 5
A project has been underway for the last six months While discussing its status with two out of the five team leads, the project manager notices an information gap What plan should the project manager reference to solve this?