Question: 1
A project status report shows that the earned value (EV) is 24.5. the schedule performance index (SPI) is 0.92, and the cost performance index (CPI) is 1.08. In what area should the project manager implement corrective actions?
Question: 2
A project manager notices that the project is behind schedule because materials delivery was delayed. The procurement team informs the project manager that new government-imposed rules for the procurement of these materials caused this delay.
In what plan should these new rules be documented?
Question: 3
During a project's initiation, project manager A realizes that the project is dependent on and linked to other projects Project manager A attempts to change the plans of these other projects. The other project managers feel that project manager A has overstepped boundaries.
Which document does project manager A need to revisit?
Question: 4
The project manager discovers that the vendor did not perform software technical testing. Which document confirms whether the vendor should do this testing?
Question: 5
A new project manager resumes a project in its execution phase. During a project status meeting, a team member reports an issue shared by a stakeholder. What should the new project manager do?