Question: 1
A project manager creates an internet project repository available to all stakeholders. The expectation is that all updated documents will be shared via this repository.
What type of communication does this describe?
Question: 2
A key project stakeholder requests that the project management plan ensures that actions are taken to prevent defects. What should the project manager use to document how the project will demonstrate compliance with this requirement?
Question: 3
The project manager of a pipeline project hires a construction contractor using a cost plus fixed fee (CPFF) contract, the contractor provides the project manager with an estimate of US$50,000, and a fixed-fee amount of US$5,000. When the pipeline is completed, the construction cost is US$60,000.
What amount should the contractor be paid?
Question: 4
As part of a project, a new plant is being constructed in a typhoon-prone area. This may impact the project s schedule and quality. What should the project manager do to address this?
Question: 5
A project team completes the identification of project and product requirements. Which of the renewing were used to accomplish this?