Question: 1
A team completes a prototype of a new product utilizing the latest technology. During testing it fails to meet performance specifications
What should the project manager do?
Question: 2
During a status meeting, a stakeholder requests a new requirement that was previously unidentified. What should the project manager do?
Question: 3
A project manager is conducting testing on product attributes. What should the project manager use to validate compliance?
Question: 4
Company A wants to subcontract the installation of a factory's building management system to company B. After some adjustments and a review of key stakeholder feedback, company B's project manager needs to develop the project charter for approval.
What should company B's project manager consider as an input when developing the project charter?
Question: 5
During a project's execution phase, a developer suggests a design change that will improve system performance without incurring additional costs.
What should the project manager do first?