Question: 1
Late in a project's implementation stage the project manager discovers that a requirement was omitted. What should the project manager do next to correct this?
Question: 2
Work on a project passes the customer acceptance test and the customer expresses appreciation. What should the project manager do to close the project?
Question: 3
A project sponsor approves a significant change to project scope that requires additional work and new deliverables from an external provider. What should the project manager do?
Question: 4
An organization is completing a critical milestone during the construction of residential properties. The project is fully sponsored by the government. Ten days prior to completion of this key project phase: affected community members begin a four-day protest causing the project to be put on hold.
What should the project manager do?
Question: 5
A design protect is ready to be transferred to production. What activity is required for phase closure?