Question: 1
A project's initial budget is USS200.000, but its actual cost (AC) to date is US$160,000. During an evaluation of the project's progress, the project manager determines that the cost performance index (CPI) is 0 8, which exceeds the budget baseline.
If current performance is maintained, what is the estimate to complete (ETC)?
Question: 2
While preparing a project charter for a new project, a project manager reviews lessons learned from previous projects the lessons learned documents show frequent issues with low engagement levels and stakeholder misalignment on project objectives.
What should the project manager do to avoid repetition of this issue in the new project?
Question: 3
A project manager realizes that an issue that occurred several weeks ago has negatively impacting the schedule. When the mitigation plan is initiated, it fails because the required resources are now unavailable.
What should the project manager have done to avoid this?
Question: 4
After preparing the final project report, the project manager realizes that the stakeholder distribution list is incomplete. What should the project manager do?
Question: 5
A project is three weeks behind schedule and the baseline finish date is two months away. The management team states there is no budget overtime pay.
What Should the project manager do to complete the propel on schedule?