Question: 1
A project manager must track schedule variances over time. What tool or technique should be used to determine whether or not the variances are within acceptable limits?
Question: 2
A project manager must obtain approval for a network cabling project. After preparation of detailed project information. some team members remain dissatisfied, as the selected equipment is new and insufficiently tested. The project manager determines that the equipment meets technology needs.
What skills should the project manager use to obtain team consensus and sponsor approval?
Question: 3
The implementation of a large financial management software application has been successfully completed. The project manager is preparing to transfer the product to the IT support team
What is the support team responsible for after the hand-off is approved?
Question: 4
During project execution, a project team develops a new response for an existing risk that will reduce the schedule by 30 days. What document should the project manager update?
Question: 5
A project manager assumes a three-year, multiphase project with tight timelines. stakeholder schedules permit time for addressing only essential activities.
How should the project manager handle updating the lessons learned?