Question: 1
In the late stages of project planning, a project manager develops a risk response plan with subject matter experts (SMEs) and project team members. The team identifies additional efforts required to mitigate the risk of poor quality in some deliverables.
What should the project manager do next?
Question: 2
An IT group rejects a project deliverable citing noncompliance with existing processes. The project team believes that reworking the deliverable would delay project delivery by three weeks. What should the project manager do?
Question: 3
While estimating project costs, a project manager works with a subject matter expert (SME) who has historically underestimated the effort necessary to deliver project requirements. In all other areas, however, the SME is a good contributor, well respected, and often requested by stakeholders.
To proactively mitigate the risk of underestimation, what should the project manager do?
Question: 4
A project manager has been receiving enhancements to a product that will be launched in five months. What should the project manager do next to ensure that these enhancements are included in the product release?
Question: 5
A project team member requests a change that will impact the project's major functionality. A subject matter expert (SME) conducts an impact assessment and determines that this change will affect the project's timeline.
What should the project manager do?