Question: 1
A joint venture project is waiting for legal closure. Further evaluation reveals that it critically conflicts with the agreement from another joint venture.
What should the project manager do next?
Question: 2
The project team is behind schedule and believes that by omitting the documentation of lessons learned, the desired delivery due date can still be reached. What should the project manager do?
Question: 3
A vendor ships a material four working days ahead of the activity start date. If the material requires two working days to be transported, and another working day for warehousing procedures at the purchasing company before being delivered to the project team; which of the following is true about the anticipated delivery status of this material?
Question: 4
During a project's execution phase, the project manager receives notice from environmental authorities to stop work. What should the project manager have done to avoid this?
Question: 5
A complex project is closing and many project team members report negative experiences. The project stakeholders from various areas of the organization may never work together again As part of the project's requirements; the project manager must provide lessons learned.
How should the project manager ensure this requirement is met?