Question: 1
An organization is implementing changes to its financial risk management portfolio The project manager has been assigned to a system upgrade project that is required to be completed by a specific date. The project has completed the planning phase and started the execution phase. After a period of time: the project manager identifies major difficulties related to resourcing constraints which will prevent the project from achieving the committed go-live date.
What should the project manager do?
Question: 2
During project initiation, the project manager learns that the charter was not approved by the proper authorities. The project manager approaches their line manager about this issue, but the line manager instructs the project manager to immediately begin work on the project plan.
What should the project manager do?
Question: 3
After completing the quality management plan, the project manager reviews the organizational process assets. They discover that a similar project was over budget due to a defect discovered during the Validate Scope process.
What should the project manager do to protect the project budget?
Question: 4
A system launched successfully and has been running smoothly for more than two weeks. The project manager requests formal acceptance from stakeholders, but one stakeholder wants to make a slight change they believe will be easy to implement.
What should the project manager do to gain formal acceptance of the change?
Question: 5
Late in a project's implementation stage, the project manager discovers that a requirement was omitted. What should the project manager do next to correct this?