Question: 1
A project manager is preparing a project closure presentation for stakeholders One stakeholder has a history of refusing to sign off on project closures
What should the project manager do prior to the presentation?
Question: 2
Company A is in the closing phase of a project and an audit reported the lack of a required archiving feature When further investigations were done it was found that archiving was not included in the development contract
What should the project manager do to address this issue?
Question: 3
An issue is raised during project execution but is not addressed This delays product authorization
What should the project manager have done*?
Question: 4
An engineering company is commissioning a new mine in a region with territorial disputes If the mine is not commissioned on time the project management company may incur enormous fines and reputational damage The project manager completes a risk analysis and chooses to purchase insurance to cover the fines if the project experiences delays
What type of risk response did the project manager use?
Question: 5
During an IT implementation project the project team is learning about new technology Adopting some of this new technology will result in reducing the projects schedule and cost
What should the project manager do?