Question: 1
Upon completion of a new shopping mall the project manager needs to determine if the project meets the planned success criteria To what should the project manager refer?
Question: 2
The sponsor of a project requests to see a prototype for a project deliverable Three options are provided and the sponsor accepts one of these options While implementing the deliverable a team member informs the project manager that the approved sample does not meet a particular government standard and will not be suitable for use
What should the project manager have done to avoid this mistake*?
Question: 3
During a project's execution phase the customer insists on additions to product requirements What should the project manager do first?
Question: 4
Detailed design has begun on a firm fixed price (FFP) contract, and the statement of work (SOW) has been dearly defined for the consultants Now, an expert communicates to the consultants that additional work is needed
How should the project manager proceed?
Question: 5
During the deployment of an enterprise resource management system, the financial director resigned and is replaced by a new one What should the project manager do?