Question: 1
A project manager is preparing the quality management plan for a project with deliverables that require a 25-year warranty. What should the project manager do to determine the quality level to be used?
Question: 2
Near the end of a project the change control board (CCB) decides that the team must integrate a new subsystem Due to technology changes, the project manager had no practical recourse other than to accept the change and move on despite it impacting the schedule
What should the project manager do to handle this unexpected change?
Question: 3
A project manager is running a company-wide project involving different business units During a planning session, the project manager notices that each unit's specific requirements are of no interest to other units, which affects the quality of the meeting
What should the project manager use to resolve this?
Question: 4
A marketing team's project manager is working on improving an employee engagement project The marketing team will be creating materials, events and messages to increase engagement
How should the project manager approach stakeholder engagement*?
Question: 5
An organization's objectives require the reduction of costs associated with future failures What should the project manager do when budgeting cost?