Question: 1
A large software development project, with high revenue and more than 50 people on the team is in the execution phase The requirements have been collected, and the project team finished the first module in two months The results were presented to the stakeholders and the team received approval However the stakeholders informed the team that new requirements were not previously communicated
What should the project manager have done during the execution phase to avoid this problem?
Question: 2
A project is progressing but stakeholders show little interest and supply minimal effort. To engage the stakeholders what should the project manager do first?
Question: 3
While generating the status report for a budget-constrained project, the project manager identifies that the project is one week behind schedule What should the project manager do to bring the project back on track?
Question: 4
A project manager joins a project late during its execution phase Upon reviewing the issue log the project manager notes that many changes occurred since initiation Resistance to these changes and disagreements among stakeholders were frequently documented as issues
Without familiarity with the project's background and the reasons for these changes what should the project manager do next'?
Question: 5
During a projects execution phase, the project manager notices that internal email communications have been copied to external clients. What should the project manager do first?