Question: 1
According to the information in the grid, what is the estimate at completion (EAC) for this project and what does it represent?
Question: 2
An overseas project has a budget of US$4 million. Due to a decrease in the currency exchange rate, the project's cost performance index (CPI) is 0.91. What should the project manager do to address this issue'?
Question: 3
During the construction of a port, a nearby fishing community blocks the projects access route and demands the construction or a paved road connecting the community with the port. This increases the project cost by five percent.
What should the project manager have done to prevent this?
Question: 4
Faulty vendor supplied parts must be returned and reordered. Based on previous experience with this vendor, the project team has already identified this as a risk?
What should the project manager do to record this?
Question: 5
After completing the project charter, the project manager sends it to the project stakeholders. What should the project manager do before starting the project planning process?