Question: 1
A project manager assumes a multi-country project that is expected to provide the company with significant tax benefits. During the execution phase, the project manager encounters process exception's and changes that were not included in the project charter.
What should have been considered during project initiation to avoid this?
Question: 2
In a control chart, three measurement points in a process are below the mean and within control limits. Four measurement points are above the mean and outside the control limits.
How is this process performing?
Question: 3
A protect manager develops a business case during project initiation What areas should the project manager consider when developing the business case?
Question: 4
A project manager is initiating a highly controversial project with numerous stakeholders. Several of these stakeholders fail to support the project.
What should the project manager use to manage stakeholder expectations?
Question: 5
A project learn is evaluating whether promotional activities should be outsourced or conduced internally. What process is the team implementing?