Question: 1
During a project review meeting, a team member disagrees with a collage on the project's status. Key millstones are dependent upon the completion of these two team members' tasks. The conflict is negatively influencing other team members, who now doubt their own.
What should the project manager do?
Question: 2
For a highly regulated financial-industry project, the team develops risk response strategies. During execution, the project is delayed, and the sponsor asks the project manager to evaluate the effectiveness of these strategies.
What should the project manager do?
Question: 3
While preparing for a kick-off meeting, a project manager learns that some project activities were underestimated, which will cause delays and cost overruns It is not possible to update project planning before the kick-off meeting
What should the project manager do?
Question: 4
A client informs the project manager that a team member is unacceptable for a project that is behind schedule. However, the client is unwilling to share their reasons.
Question: 5
A project manager and project team identify that the number of detects can be reduced by focusing on specific modules. They investigated and prioritized the area with the most defects and reduced them.
What did the project manager and team use?