Question: 1
The project sponsor is inappropriately requesting status reports from individual team members. The project manager plans to meet with the sponsor to discuss the issue
To what should the project manager refer prior to the meeting?
Question: 2
The project manager for a new project wants to discuss project execution methodology with all stakeholders. During what meeting should the project manager first discuss this?
Question: 3
A project has been ongoing for a year Early in the year, its schedule performance index (SPI) was 12, its most recent SP1 is 0.7. What did the project manager use to track and communicate this information?
Question: 4
A project manager is developing an organizational chart and requests the use of a specialized resource from another department. The functional manager of that department understands the value of this resource but denies the request
What should the project manager do?
Question: 5
A project manager is working on a technical project with a technical lead who is experienced, highly knowledgeable and works well with the team. The technical lead is usually on time with deliverables but their documentation often requires rewriting for formatting and contextual quality
How should the project manager address this?