Question: 1
A new project manager is assigned midway through a project After conducting a project performance review, the project manager discovers that a supplier is unable to finish the work At this stage, switching suppliers will carry considerable risk however not switching will result in cost increases and schedule delays
What should the project manager do next?
Question: 2
During protect execution, a protect manager teams that a team member's functional manager believes they should not execute a certain task. What document should the project manager review to resolve this?
Question: 3
An important project stakeholder is replaced, and their successor is unhappy with the progress and direction of the project. The new stakeholder wants to implement changes that will cause delays
What should the project manager do?
Question: 4
An independent, third-party auditor conducted scope verification The client questions the impartiality of the third-party's report What should the project manager do?
Question: 5
During a progress review of a project near completion, there is an indication that a work package may require some major rework. This could affect the completion date
What should the project manager do first?