Question: 1
Which conflict resolution technique offers project managers the least positive option for resolution
Question: 2
You are the Project Manager doing earned value analysis when you find out that SPI = 1.12 and CPI is 0.75. What can be said about the project status?
Question: 3
One of the Project stakeholders requested a change to the project. This change will result in the change of the project end date. The project manager discussed the potential impacts of this change with the stakeholder. What is the best method a project manager can take to resolve this?
Question: 4
A project manager has recently been assigned to a long-running project and wants to know who the key influences are on the project and what their level of involvement is. The best document to gather this kind of information is:
Question: 5
You are the project manager of a village housing construction project. You are interviewing the village owners to determine their requirements, needs, and desires for the home construction. What is this technique called?