Question: 1
Why should a project team reduce the work in progress?
Question: 2
A team's technical lead believes that manual testing should be conducted by junior team members below their level. The junior team members think it is unfair and refuse the tasks.
What should the scrum master do?
Question: 3
Due to its complexity, a new team member struggles with developing a concise user story.
What advice should the agile practitioner give to assist with developing the story?
Question: 4
Based on the burndown chart, what is the iteration's status?
Question: 5
A new product owner shares the product vision during the team launch event. The team asks for clarification on the product roadmap and its high-level features.
What should the product owner do?