Question: 1
A new learn member asks what changes could accelerate a change to the project plan. What should be the proper response?
Question: 2
Early in a project stakeholder analysts is performed, however an organizational restructure redefines key rotes What should the protect team do?
Question: 3
Senior management is frustrated at the lack of a detailed implementation plan that shows exactly when the project will end and when all requirements will be met. The team has been using a rolling wave planning approach so far on the project.
How should the agile practitioner explain to senior management the benefits of this approach?
Question: 4
What of the following is not a step in the Value Stream Mapping process?
Question: 5
Which three of the following points about the daily Scrum are TRUE? (Choose three.)