Question: 1
An iteration prior to a release that includes final documentation, integration testing, training and some small tweaks is called:
Question: 2
Analyzing the current organizational processes, per project requirements, and making needed process changes is called:
Question: 3
At the end of first iteration, the team finishes User Stories A, Band 50% of C. What is the team velocity?
Question: 4
Suppose 8 new members joined the development team, and the team size is now 15. The daily Scrum is getting noisy and exceeding the 15 minutes time-box. What is the most effective way to address this situation?
Question: 5
While developing a story during the iteration, team discovered new tasks that were not identified earlier. A newly discovered task is such that the User Story cannot be completed during the iterations. What are the most appropriate actions for the team to perform?