Free Practice Mock Questions Set 21-25 (Quiz # 5) for BCS ISEB-PM1 Exam, according to official BCS Foundation Certificate in IS Project Management exam syllabus topic # 1
Response Planning is the responsibility of the functional areas and considers ___________.
Answer : D
For communication to occur, there must be ___________.
Answer : A
Communication in both project and non-project-driven organizations should occur in __________ directions.
Answer : E
The most rapid Estimate Costs technique is ___________.
Answer : C
Resource leveling _____________.