Question: 1
You are the project manager of a project that's currently in the definition phase. After your first meeting, the project sponsor has asked to see the integrated project management plan.
In this scenario, which of the following best describes the importance of an integrated project management plan?
Question: 2
You are leading a large-scale information technology project to migrate your company's data to the latest hardware. The delivery is being led by third-party suppliers, who were not involved in the design phase. The supplier has completed their capacity planning and has raised a potential risk that the current data may exceed the storage capacity of the new hardware purchased.
What type of risk response would you choose to mitigate this risk?
Question: 3
According to Herzberg's two-factor theory, which of the following best illustrates a leader who positively impacts team performance and motivation?
Question: 4
Which of the below would not usually be recorded within a change request?
Question: 5
You are a project manager leading a newly formed project team. Which factor should NOT influence your decision when assigning roles and responsibilities to your team members?