Question: 1
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
Which of the following is least likely to improve a large earthmoving contractor's productivity?
Question: 2
When the project plan is implemented:
Question: 3
A work breakdown structure (WBS) is developed because:
Question: 4
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
In Rensis1 4 model system, the exploitative-authoritative management style is one in which:
Question: 5
After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client.
A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.
What is the cost variance (CV)?
A BCWP-ACWP = 105,000-110,000 = -5,000
B ACWP-BCWP = 110,000-105,000 = 5,000
C BCWS-ACWP = 100,000-110,000 = -10,000
D ACWP-BCWS = 110,000-100,000 = -10,000
Answer : A